Exterior shot of the ICF construction before the forms are removed.

Periwinkle Luxury Home Construction Update 8/23/18

Welcome back to Periwinkle Grand Harbour, one of Cayman Structural Group’s large scale luxury developments! August has been a busy (and rainy) month on the Periwinkle job! Pretty much all of our effort is going into placing and pouring the ICF walls right now. You can see...
26
JUN
2018
The wooden frame under the stairs get framed out.

Periwinkle Luxury Home Construction Update 6/26/18

Welcome back to Periwinkle Grand Harbour, one of Cayman Structural Group's large scale luxury developments!
06
JUN
2018
Early work on one of the building's staircases.

Periwinkle Luxury Home Construction Update 6/05/18

With the first section of ground level walls completed at these Cayman Island townhouses, our crews have moved on to the staircases, porches, and beginning stages of the second floor.
18
MAY
2018
The reinforcement for the lintel beam is lowered in.

Periwinkle Luxury Home Construction Update 5/18/18

Our crews reached a big milestone on these buildings since our last update.
07
MAY
2018
The reinforcement for the lintel beam is lowered in.

Periwinkle Luxury Home Construction Update 5/07/18

Two more of the homes in the multi-structure Periwinkle development got their start this week.
20
MAR
2018
Exteriors of the houses with new patio roofs.

Periwinkle Luxury Home Construction Update 3/20/18

Several of the roofs on this multi-building development received their spray foam insulation this week.
02
MAR
2018
Crew member climbs scaffolding.

Periwinkle Luxury Home Construction Update 3/2/18

Greetings from the Periwinkle luxury home construction site. Construction is moving along well, as we make progress on portions set in motion a few weeks ago. Window sill plaster is underway to the appropriate structures, as well as the internal walls. The building that was...
17
FEB
2018

Periwinkle Luxury Home Construction Update 2/17/18

The cleaning phase has begun for certain structures, as the concrete pouring moves to others. A window and staircase has been squared and constructed inside one home. Plastering has begun on the staircase as well. Straightening edges to certain structures is underway, including...
06
FEB
2018

Periwinkle Luxury Home Construction Update 2/6/18

Several homes have had their footing pillars poured, and strip work to more footings is underway. The nature of this project requires certain homes be farther along in construction than others. The photos below are actually a great representation of the initial stages of a...
17
JAN
2018

Periwinkle Luxury Home Construction Update 1/17/18

Last update we showed photos of reinforcements being constructed on the ground floor. Now you can see some of those structure begun to take shape. Several buildings have to be poured still, yet some of the other structures are nearing completion of their base. Some workers can be...
12